  1. Surface Preparation
    • Brush away loose contamination on the substrate to be coated.
    • Bio-wash for killing fungus where necessary
    • Roughen surfaces by wire brush manually.
    • All surfaces must be clean and free from laitance, dust, dirt, oil and grease.
    • Please check Moisture level and pH level in walls/roof/terrace/ceilings. The moisture level should be below 12% and pH should be in the range 7-9.
  2. Mixing Instructions
    • Turn pails upside down 8 hours prior to application. This will allow coating to become softer and easier to mix.
    • Thoroughly mix the contents of containers using stirrer/mixer. Over-Mixing more than 5 minutes may destroy particles, thereby reducing insulating capabilities.
    • Thinning/Dilution of the material using water is not recommended.
    • Stir the paint occasionally before each use.
  3. Product Application
    • The surface should be moist/water wash before application. However avoid puddling/ponding of water.
    • Apply first coat with brush on the cleaned and washed surface.
    • Apply second coat after a gap of 1-2 Hours.
    • After completion of full coating, it should be allowed to cure for 24 hrs. Drying time may vary due to temperature / humidity and surface condition.
    • Ensure that the coated area does not come in contact with water for atleast one hour.
    • Apply with a quality brush, or roller.
    • For best results, Apply when surface and ambient temperatures are above 13°C and below 32°C.
    • After completion of full coating, it should be allowed to cure for 24 hrs. Drying time may vary due to temperature / humidity and surface condition.
  4. Product Limitations
    • Not recommended for immersion conditions.
    • Not to apply the product below 15°C and above 40°C